Skip Navigation Links
Skip navigation links
VUSD
Board Of Education
Schools
Departments
News
Intranet
Resources
Employment
Skip navigation links
Citizens' Oversight Committee
Oversight Board Resolution
Oversight Committee Bylaws
Summary of Facility Projects
Schedule of Committee Meetings & Minutes
Potential Funding of Projects
Estimated Bond Proceeds
Developer Fees
Moodle
Renaissance Place
Summary of Facility Projects 

  Vista Unified
Upcoming Projects

PROJECT

COST

1.)   New High School

$  51,816,000

2.)   GPA Expansion

$  38,920,708

3.)   New Continuation High School

$    8,116,000

4.)   New Middle School

$  23,051,977

5.)   Six New Elementary Schools

$  83,336,238

6.)   Environmental Mitigation of New Sites

$    5,000,000

7.)   Washington Multipurpose Building

$    3,346,506

8.)   RBV High School Stadium

$    1,684,204

9.)   Two New Temporary Elementary Schools

$    2,000,000

10.) Modernization of Existing Schools

$  19,148,577

11.) Improvements at Existing Schools

$    7,205,000

12.) Educational Technology Infrastructure

$    6,000,000

Total:

$249,625,210